.3.3. Model Run and Output DMIs
The Forecast Model is run in rulebased simulation with the Forecast Model ruleset. To complete a simulation, use the following steps:
- Open and load the Forecast Model ruleset.
- Adjust the Run Control in the model to have an Initial Timestep of December 31 of the previous year (Start Timestep of January 1) and a Finish Timestep as December 31 of the current year.
- Run the model.
-The simulation may take a minute or two to complete.
- Save the model with a name that designates the month of the forecast and forecast exceedence percentage.
- Invoke the DBDSSForecastOutputToWaterOpsGWHeadsAndStorages and DBDSSOutputForecastDataForWaterOps database DMIs by invoking the DMI group named DBDSS_OutputForWaterOps.
- Exit the Forecast Model.
- Rename output DSS files to identify the month of the forecast and forecast exceedence percentage and move the DSS files to a location for this simulation based on your organization’s or agency’s protocol.