We would like to complete for RiverWare 6.6 items 1 through 6 (and not 7 and 8) on this "additional feature list" discussed with the URGWOM team in a webinar meeting. (See: http://cadswes2.colorado.edu/~philw/2014/TeaCup/CompletionProposal-2014-11-12.html):
The table below shows estimates from the original task analysis of the features we would like to complete for RiverWare 6.6. These estimates are provisional -- taken primarily from the original development plan analysis. The intention is to attempt to complete these within two full weeks of Phil's development time. I think this can be done on an accelerated schedule. The Flowlines development will likely be not completely fleshed out -- the basic features estimate was 78 hours, not including a legend.
Est (hours) |
Task | |
1 | 8 | Teacup Legend |
2 | 8* | Background Images |
3 | 8 | Output Canvas Viewer Dialog |
4 | 8 | Model Reports: Inclusion of Output Canvas |
5 | Misc. Polishing: | |
8 | "Setting" Enhancements | |
4 | Teacup Vertical Axis | |
2 | Teacup Groups: configurable maximum height (pixels) | |
6 | 40* | Flowlines |
86 | TOTAL |
*Substantially reduced from original estimate.
---