Project: BOR IDIQ - 19 Alb Enhancements to RPL
(Phil, 3-21-2014).
Revised task list:
Time spent so far. Note: other than the Monday 3-17 meeting (1 hour, 5 people), this doesn't include Patrick's discussion time after 3-6, nor any of David's or Jim's time.
Task: | 1 | 2 | 3 | 4 | 5 | TOTAL |
Status: | Done | Done | Done | Done | Done* | |
Patrick (as of 3-6) |
45 | 0 | 14 | 9 | 2 | 70 |
Phil (as of 3-20) |
30.25 | 34.5 | 64.75 | |||
3-17 Meet (5) x 1 hr |
5 | 5 | ||||
Total: | 45 | 35.25 | 14 | 9 | 36.5 | 139.75 |
![]() |
||||||
Estimate: | 40 | 40 | 24 | 32 | 16 | 152 |
Remaining: | -5 | 4.75 | 10 | 23 | -20.5 | 12.25 |
Total remaining hours: 12.25 (but see note above).
*(5) Including several post-development review requests. See feature doc.
TASK | Possible "TO DO" ... | EST (hours) |
(1) | For slot/timestep cells with a known Rule Priority (whether shown or not) -- in the Open SeriesSlot dialog and the SCT -- add a context menu operation to open the Rule. | DONE |
(2) | For "completeness", show also tooltips on slot/timestep cells for flags (with the exception of the obvious ones: "I", "O"). | DONE |
(3) | Add to the RPL Palette's two function tabs the Name Filter (which had been added to the RPL Object Selector) ... See top of screenshot. | 8 |
Phil