Workspace Barebones Ornaments for RiverWare 6.5

See Proposal Document -- 10-23-2013
http://cadswes2.colorado.edu/~philw/2013/WsOrnaments/BarebonesProposal.html

(4) Development Estimates

Task   10-23
Est.
  10-25
Est.
  Description
Days Hours Hours
1 2.25 18 16.75* Proposal and Development Planning (this and prior document).
2 0.5 4 9.5* Data Model: with basic data serialization (excluding image serialization).
3 1.25 10 12 New Dialog: Ornament Editor
4 1.0 8 12 Data Model: Image Serialization
5 1.25 10 16 Ornament Graphics Items
6 0.25 2 4 Completion Testing, including Print and Image Export Testing
7 0.25 2 3 Developed Feature Documentation
8 --- --- 6 Post-Development Review Changes (1 to 6 hours, depends of course).
  6.75 54 79.25

TOTAL estimate

*Actual Time Spent (over four days: 10-22 ... 10-24) -- Total: 26.25 Hours.
Remaining Time (10-25 Estimate, Tasks 3 through 8): 53 Hours.

---